December 9, 2010

Week of December 6

This week level 1 is full of activity. We're hanging sheetrock so the classrooms take shape and we've installed fireproofing at the steel beams. The ironworkers are welding the north stair together and the mechanical subcontractor continues to install their support structure at the ceiling for their pipe.

The attic space is also very active. Ductwork is being installed as well as fire sprinkler and radiant panel pipe. We plan to start installing the ceiling grid next week.

Outside we're setting formwork for the south stair entrance and installing metal flashing in the window openings.