December 12, 2010

Week of December 13

This week we're finishing the drywall at level 1 and installing the structure for the radiant metal panel ceiling supports in the classrooms. We're continuing to install ductwork, fire sprinkler and radiant panel piping in the attic space. Level 3 ceiling framing starts this week; there will be a lot of bodies upstairs between the mechanical rough in and the framing contractor.

Outside we're continuing to set forms for the south stair concrete. On the roof the sheet metal contractor is finishing up the parapet cap metal and getting ready to install the wall panels.

Looking ahead, the north wood windows and the south, east and west fiberglass windows are scheduled to arrive late December to early January. We look forward to getting them on site and buttoning up the outside of the building.