November 15, 2010

Week of November 8

We received word last week that the renovated Northup Hall will be called T.J. Day Hall. T.J. Day is a 1971 graduate of Linfield College and a member of the Board of Trustees. We look forward to giving him a tour of the new building upon completion.

We had some rainy weather last week while we finished up the steam line work at the NE corner and started excavation for the south stairs and ramp. We hope for drier weather this week, but know that the forecast is not in our favor. Thankfully, we're dry on the inside.

Level 1 and 2 framing is in full swing and electrical rough is following closely behind. The engineer is reviewing the mechanical, electrical and plumbing coordination drawings and we plan on installing attic ductwork soon.

Attached is time-lapse video showing the erection of the steel beams for the bridge at the Central Hall. Check it out!

http://www.flickr.com/photos/irv/5119248336/in/set-72157625019931665/