This week we've been blessed with good weather. The majority of the asphalt shingle roofing has been installed and the photovoltaic stand offs on the south elevation are complete. We're pouring the concrete for the ground floor classrooms and infill trenches this week. Our crews are installing the window wrap mock-up at the south elevation in preparation for the new windows. We're laying out the walls at the second and third levels in preparation for metal stud framing, which starts at the end of the month.