September 7, 2010

Week of September 7

School is back in session and the campus has come alive!

This week the exterior crew will be re-building the flat roof. The first structural steel beam will be set today and the rest of the "pop-up" roof framing will follow. The interior crew is finishing up the demolition and preparing to pour concrete for the basement footings on Friday. We are measuring up for the gutters today. As soon as they are installed we can start "drying in" the roof with asphalt shingles on the gable/pitched roofs and membrane roofing on the flat part.

Inside the trailer, the team is working on the final details for the solar panels, which will be installed on the south elevation facing the courtyard.

The light rains aren't impeding our progress, but we're crossing our fingers for better weather in the coming weeks.