September 27, 2010

Week of September 27

As the month comes to a close we are doing our best to dry in the building. The flat roof membrane base sheet will be complete today. Asphalt shingle roofing at the north elevation starts on Wednesday; we are chasing the built in gutter installer around the building with our roof work. The solar panel installers are doing their stand off layout at the north elevation today and we should see some "feet" installation by the end of the week.

Inside the building we're demo'ing the concrete at the ground floor in order to build the tiered classrooms. We're also removing the concrete slab between the first and second floors for the Central Hall stair. This will be a noisy, but productive week for the project.