August 3, 2010

July Progress

Walsh Construction Co./OR broke ground on July 7 and work has progressed at a steady pace. The phone and data lines have been relocated along the south side. New utility installation is in progress and excavation for below grade waterproofing has begun. Interior demolition started last week and the majority of the ground floor interior walls have been removed. We're cutting out the opening for the south entrance this week. Please be sure to check out the web camera links on the lower right hand side of this page. Stop by often to check out the progress of the new building, which is scheduled to open up Summer 2011.